Voiron railway bridge

Illustration image

5 June 2018 - Projects update and handover - France

May saw the joint venture composed of Campenon Bernard Régions (VINCI Construction) and VINCI Construction Terrassement successfully slide the Voiron railway bridge into place, on behalf of SNCF Réseau.

Lasting 102 hours non-stop, this operation, involving 35 VINCI Construction Terrassement people (one team from Centre Terrassement Mancuso and one from Benedetti-Guelpa), formed part of the urban renewal project of the Voiron region agglomeration community.