On 13 January 2012, Socogim IDF (VINCI Construction France), as project developer, inaugurated Melun's municipal technical centre in Vaux-le-Pénil (Paris region), built within the framework of a PPP due to last for 23 years and 10 months. Maintenance of the centre has been awarded to VINCI Facilities (VINCI Energies). The works, involving the construction of a 2,100 sq. metre building and the refurbishment of a 400 sq. metre building, were completed in eight months by Verdoïa (VINCI Construction France); value: €2.7m.