€100.550 The share price increased by +0.25 %   15/11/2024 17:38

Soil improvement for Jakarta Airport

Illustration image

10 October 2012 - New contracts - Indonesia

Menard Asia, a Soletanche Freyssinet subsidiary (VINCI Construction), has just been awarded the soil improvement contract for the new phase of works at Terminal 3 at Jakarta International Airport. Starting in October 2012 and taking 8 months to complete, the operation aims to consolidate a total surface area of 346,075 sq. metres using the controlled modulus column (CMC) technique. Contract value: €23m. The company had already participated in the first phase of works, in 2011, using the same technique to treat a surface area of 65,000 sq. metres.