On 21 May 2015, in central France, the presidents of the Cantal and Correze departmental Councils visited the worksite on the RD120 secondary road (Cantal) being implemented on a public-private partnership basis by Eurovia Dala – Clermont-Ferrand office and VINCI Construction Terrassement (Major Projects Division/VINCI Construction). The contract covers the financing, design/construction and upkeep/maintenance of more than 10 km of this road located to the northwest of Aurillac. Begun in October 2014, the earthworks have been 70% completed, and five of the seven civil engineering structures planned have already been built. Entry into service is scheduled for December 2015.