Raising platform levels in Gisors

Illustration image

24 July 2020 - Projects update and handover - France

In Normandy, on behalf of SNCF Réseau, VINCI Construction Terrassement has increased the height of 1,200 lm of platforms; work involving temporarily stopping rail traffic was often carried out at night, by 50 workers.

Launched in January, the works were completed in mid-June. This project involved 200 6-lm walls – 600 warning slab units –, 2,500 m3 of cut-and-fill and 350 t of mix, applied by hand.